Error description

  • With the upcoming GA release of CICS
    Transaction Server for z/OS Version 5
    Release 4, a compatibility APAR is
    required for pre-V5R4M0 CPSM regions
    before they start communicating with
    V5R4M0 CPSM regions.
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED: All CICSPlex SM V5R1M0, V5R2M0 and V5R3M0    *
    *                 Users                                        *
    ****************************************************************
    * PROBLEM DESCRIPTION: A compatibility APAR is required to     *
    *                      tolerate a task load of zero (0) in a   *
    *                      CPSM WLM target region, which can occur *
    *                      due to changes introduced in CICS       *
    *                      Transaction Server for z/OS Version 5   *
    *                      Release 4 (CTS V5R4M0).                 *
    ****************************************************************
    * RECOMMENDATION: After applying the PTF that resolves this    *
    *                 APAR, all CMASes and MASes must be           *
    *                 restarted.  Note that the restarts do not    *
    *                 need to occur at the same time.              *
    *                                                              *
    *                 This fix is being provided across all        *
    *                 pre-V5R4M0 supported releases of CPSM as     *
    *                 follows:                                     *
    *                                                              *
    *                 -  CPSM V4R1M0 - APAR PI81778                *
    *                 -  CPSM V4R2M0 - APAR PI81778                *
    *                 -  CPSM V5R1M0 - APAR PI81780                *
    *                 -  CPSM V5R2M0 - APAR PI81780                *
    *                 -  CPSM V5R3M0 - APAR PI81780                *
    *                                                              *
    *                 While the restarts do not need to occur at   *
    *                 the same time, all pre-V5R4M0 CPSM CMASes    *
    *                 and MASes should be restarted to run with    *
    *                 the PTF that resolves the APAR for its       *
    *                 release, before connecting into a CPSM       *
    *                 network that contains CPSM V5R4M0 CMASes     *
    *                 and MASes.                                   *
    ****************************************************************
    Updates made in CTS V5R4M0 change most CPSM tasks in a MAS
    running with both CICS and CPSM at the CTS V5R4M0 level,
    including all long running MAS tasks, from user to system tasks.
    As such, it is possible for a CPSM target region running both
    CICS and CPSM at the CTS V5R4M0 level, to have a task load of
    zero (0).  Updates are required for pre-CTS V5R4M0 CPSM regions
    to accommodate this:
    
    -  MAS method EYU0WNAL (WNAL), which runs in a CPSM WLM routing
       region during route selection processing, must be updated to
       correct a situation where a task load of zero (0) for a
       target region could result in an affinity not being created.
    
    -  CMAS methods EYU0WABA (WABA) and EYU0WABB (WABB), which run
       in a CMAS to create WLMAWAOR (WABA) and WLMATARG (WABB)
       resource table records when requested through the CPSM API,
       WUI or Explorer, must be updated to correct a situation where
       a task load of zero (0) for a target region could result in
       the ROUTEWGHT attribute being incorrect.
    

Problem conclusion

  • Updates have been made to WNAL, WABA and WABB to allow for
    target regions with a task load of zero (0).
    

Temporary fix

Comments

APAR Information

  • APAR number

    PI81780

  • Reported component name

    CICS TS Z/OS V5

  • Reported component ID

    5655Y0400

  • Reported release

    80M

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    YesHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2017-05-17

  • Closed date

    2017-05-24

  • Last modified date

    2017-06-20

  • APAR is sysrouted FROM one or more of the following:

    PI81778

  • APAR is sysrouted TO one or more of the following:

    UI47509 UI47511 UI47512 PI83329

Modules/Macros

  • CJA0WNAL CJB0WNAL CJC0WNAL CJD0WNAL CJE0WNAL CJF0WNAL EYU0WABA
    EYU0WABB EYU0WNAL
    

Fix information

  • Fixed component name

    CICS TS Z/OS V5

  • Fixed component ID

    5655Y0400

Applicable component levels

  • R00M PSY UI47512

       UP17/05/26 P F705 ¢

  • R80M PSY UI47509

       UP17/05/26 P F705 ¢

  • R90M PSY UI47511

       UP17/05/26 P F705 ¢

Fix is available

  • Select the PTF appropriate for your component level. You will be required to sign in. Distribution on physical media is not available in all countries.

[{"Business Unit":{"code":"BU058","label":"IBM Infrastructure w\/TPS"},"Product":{"code":"SSGMGV","label":"CICS Transaction Server"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"5.1","Edition":"","Line of Business":{"code":"LOB35","label":"Mainframe SW"}},{"Business Unit":{"code":"BU054","label":"Systems w\/TPS"},"Product":{"code":"SG19M","label":"APARs - z\/OS environment"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"5.1","Edition":"","Line of Business":{"code":"","label":""}}]

Document Information

Modified date:
20 June 2017